7 July 2004
The polyester coated brewery floor is laid
What a smell!
7 July 2004
The Kauri bar top is installed
Made out of a beam from a demolished warehouse in the area

7 July 2004
Peter, the gasfitter, puts up the heaters
Now we can warm the place up

7 July 2004
Mac gets the top coat of paint on one of the old sliding doors

8
July 2004
Laying the vinyl floor in the toilets

8 July 2004
Fitting the channels for the plate glass wall to divide the brewery from
the bar

8 July 2004
Installing the extraction canopy in the kitchen

16
July 2004
Final preparations for the arrival of the brewery

16
July 2004
The bottle chiller cabinet is installed

16
July 2004
The brewery arrives from Invercargill



17 July 2004
Getting those heavy tanks off the trailer is made easier with Bruce and his
forklift


17 July 2004
John polishes the inside of the Hot Liquor Tank